Project Progress: 1627 Brandywine

We're getting excited about this project--1627 Brandywine Street in Philadelphia. The building was originally a carriage house. More recently, it was used for storage. Now, we're working with the new owner to convert it to a home and studio.

The existing front.

The existing front.

The first floor will contain a garage and photography studio, with living space above. We really want to take advantage of the huge wooden roof trusses, so they'll stay exposed in the finished space. The front is in amazing condition; it's made of yellow-orange ironspot roman brick, with incredibly thin joints and great workmanship.

A detail of the oval window; look at how carefully the bricks were cut to fit it.

A detail of the oval window; look at how carefully the bricks were cut to fit it.

Carriages used to be stored in here; the large roof trusses also hold up the second floor, so that the first floor could be totally open. There's evidence that at one time there was an elevator (manually operated, of course) that could lift carriages up to the second level.

Carriages used to be stored in here; the large roof trusses also hold up the second floor, so that the first floor could be totally open. There's evidence that at one time there was an elevator (manually operated, of course) that could lift carriages up to the second level.

The second floor; the steel rods coming down from the trusses hold the floor up.

The second floor; the steel rods coming down from the trusses hold the floor up.

Some images of the proposed space.

Some images of the proposed space.

We'll keep you posted on this one. As we finish preliminary design, we're getting ready to meet with the neighbors, and then with the Historical Commission

2 Comments

Comment

Things We Do: Historical Commission Approvals

Philadelphia is an old city, whose plan was first laid out by William Penn in 1683. One of the main agencies in charge of protecting our architectural history is the Philadelphia Historical Commission (PHC). Philadelphia has a combination of historic properties (individual buildings that are protected) and historic districts (whole areas of the city that are protected). The PHC has a process in place to review any work on protected buildings and within protected districts.

Proposed Facade Restoration Drawing, 1629 Wallace Street

Proposed Facade Restoration Drawing, 1629 Wallace Street

The Commission's protections cover the exterior shape and materials of a building. The goal is to preserve existing history, and--when new development is planned--to protect the character of historic buildings and neighborhoods.

Everything is reviewed--from the materials to be used, to the restoration of existing cornices, to the shape of the roofline. We've worked with several clients to get through this process. There are several steps involved.

At the beginning of design, we will confirm that the client's property is protected. Our experience with past projects helps to inform us as to what the PHC is likely to approve, and we will try to steer our work in that direction. After putting together some preliminary drawings and taking existing-conditions photographs, we will meet with PHC staff at their office to discuss the project. They will often be able to give us a deeper historical perspective on the building, using their extensive collection of historical photographs.

1600 Block of Wallace Street, 1963 ( https://www.phillyhistory.org )

1600 Block of Wallace Street, 1963 (https://www.phillyhistory.org)

Once preliminary design is complete, we assemble an application package for the PHC Architectural Committee. This committee is made up of architects and preservationists, and their purpose is to provide guidance to us regarding the specifics of our building. We will meet with the committee to discuss the particulars of our building, and our proposed solutions. They will ultimately make a recommendation to the Historical Commission, either in favor of or in opposition to the project.

Existing Conditions at 1629 Wallace Street

Existing Conditions at 1629 Wallace Street

A few weeks later, we meet with the Historical Commission, which is the group that will make the final decision on the project. The Commission is made up of architects, preservationists, historians, and representatives from the community and real-estate development interests. We present the project to them, and they ask questions. At the end of the hearing, they will take a vote either approving or denying the project.

But wait--there's more! Assuming the project is approved, it's time for us to start on construction drawings. This involves more detailed drawings, as well as material samples. For a typical project, this might include "shop drawings" from a custom window manufacturer, brick and mortar samples, and metal finish samples. Once the construction drawings are complete and the details and material samples are assembled, we make one last trip to the PHC office to get everything reviewed. The review is just to make sure that we haven't changed anything since our Commission approval. After review, the PHC staff will stamp the drawings, and then they are ready to go to Licenses and Inspections for building permit review.

If you have a property that's listed on the Philadelphia Register of Historic Places, we can help!

Comment

Comment

Project Progress: 170 West Oxford

We've been working on a renovation and addition to this little guy in South Kensington:

That's us, in the middle.

That's us, in the middle.

This building is an L-shaped one, with a very steep staircase, tiny rooms, and closed-in windows. We'll be opening up the interior, enlarging the windows back to their original size, rebuilding the stair, and adding a third floor.

The new plans. Finished basement, living space on the first floor, two bedrooms and a bathroom on the second floor, and a master suite on the third.

The new plans. Finished basement, living space on the first floor, two bedrooms and a bathroom on the second floor, and a master suite on the third.

Rough front and rear views of the finished house, from during preliminary design.

Rough front and rear views of the finished house, from during preliminary design.

A quick rendering of the finished project.

A quick rendering of the finished project.

The project needed a zoning variance for the addition, which was granted. We are currently working on construction drawings for this one--stay tuned!

Comment

1 Comment

Working Together

I recently read an article from the November/December 2015 issue of Remodeling Magazine called "The Blueprint of a Profitable Partnership", by Victoria Downing. (I know, I know, I'm pretty far behind on my magazines.) It was a good article, giving readers some tips on what an architect is looking for in a builder. To paraphrase:

  1. Will you listen, and not impose your ideas on the architect.
  2. Will you bring the architect's design to life, or butcher it by cutting corners?
  3. Will you provide accurate estimates?
  4. Will you have great workmanship?
  5. Are you up to date on the latest products and construction methods?
  6. Will you handle material selection, if necessary?
  7. Are you organized, and do you communicate well?
  8. Do you have a record of on-time and on-budget projects?
  9. Have you done projects like this before?
  10. Do you consider the architect to be an ally? Will you bring him/her in on future projects?

This is a good list; I think most people would agree that these are reasonable things to want. And it got me thinking--what do we do in our office, to hold up our end of the bargain? How can we be good partners to our contractors?

  1. We like to listen, as well. Contractors know a lot about how buildings go together--not just how things should happen, but how the actually do happen. By visiting the jobsites and hearing how contractors deal with construction issues, we can provide better designs that will contain solutions in advance, or flexibility where there are unknowns.
  2. It's important for us to explain clearly what our priorities are. Most contractors don't want to cut corners, but they also need to be cost-conscious. By clearly describing what the priorities are, everyone can be on the same page.
  3. See #2. If we clearly describe what we want to achieve, the contractor can more accurately price the work.
  4. We believe that providing high-quality drawings and a well-thought-out design will help set a tone with the contractor that high-quality workmanship is expected. We also work to modulate the client's expectations regarding what good work costs.
  5. We do our best to stay up to date on what is happening in the field. New products come out all the time--contractors may have a different focus (ease of installation, lower cost) than the architect or client does (durability, performance, aesthetics), but if we're all keeping our eyes open and are discussing new things as they come out, the team can decide together whether to use a new solution to an old problem.
  6. Certain materials just need to perform (waterproofing or insulation, for example), while others need to have a certain appearance, too (finishes, flooring, etc). Depending on the project type and schedule, the client may want to depend more on the contractor's knowledge of what is available immediately, and we are happy to have their input.
  7. We try, at all times, to have clear, consistent communication. The best result for a project comes from everyone knowing what is happening, and having a chance to chime in on project decisions. That's part of why we try to involve the builder as early in the process as possible.
  8. Sometimes during construction, something will come up that stops the project in its tracks. It might be an unusual structural situation, or a clearance that just can't be met. We try to respond to these situations as quickly as possible, with solutions that are effective and simple. That way, the project can get back on track as quickly as possible, with minimal impact on budget.
  9. We bring a lot of experience, with many different project types under our belts. We try to learn from past projects and construction so we can constantly improve.
  10. As mentioned above in #7, we like to get the contractor involved as early as possible. That way, their input can be baked right into the design. And we're always happy to make recommendations to clients who are looking for them.

Builders--do you have a project that needs an architect?

1 Comment

Comment

The End of the Process

This is the latest project we've completed, at 3253 Sunnyside Avenue in the East Falls section of Philadelphia.  Back in July and August, I wrote two posts about the beginning of the design process. At that point, I had just finished the two initial phases: existing conditions documentation and design

Between the drawings in the first two posts and now, there was, of course, the process of construction. Below is a slideshow depicting each stage of that process.

 

 For those of you who don't want to go through the slideshow, here are some before-and-after photos:

Master Bedroom, before and after. We removed the large chimney and raised the ceiling to make the room more spacious.

Living Room, before and after.

Dining Room in four phases: 1) Existing Room, 2) New Framing, 3) Drywall, 4) Complete

The Kitchen was probably the most dramatic change. Here, a view of the existing room, the new room just after framing, and the completed space.

This was a very successful project with a great client. The construction quality is very high and everyone really took pride in it. Special thanks to the realtor and client for many of these photos.

The house is currently for sale. You can see the listing here.

Comment